WBS vs Gantt chart: how to turn a work breakdown structure into a Gantt in Jira

A work breakdown structure (WBS) and a Gantt chart are often mentioned in the same breath, but they answer different questions. A WBS breaks the project into pieces. A Gantt chart puts those pieces on a calendar, in order. In Jira you already have most of a WBS: your issue hierarchy. This guide explains the difference and shows how to turn that hierarchy into a WBS Gantt chart.

The short answer

  • • A WBS answers "what is the work?" It splits a deliverable into smaller pieces until each one is small enough to assign and finish. It has no dates.
  • • A Gantt chart answers "when, and in what order?" It puts each piece on a timeline, with dependencies between them.
  • • A WBS Gantt chart is both at once: the breakdown down the left, the schedule on the right. In Jira, epics, their stories and tasks, and their subtasks give you the breakdown; dates and issue links give you the schedule.

WBS vs Gantt chart, side by side

Work breakdown structure Gantt chart
Question it answers What has to be delivered? When does each piece happen?
Shape A tree: deliverable, work packages, activities Bars on a timeline
Dates None Start and end for every item
Order and dependencies Not shown Arrows between items, critical path
When you build it First, while scoping Next, while scheduling, and then you keep it current
Rule of thumb The children of an item add up to all of its work A parent's dates span its children's dates

You need both. A Gantt chart without a breakdown is a list of bars nobody can navigate; a breakdown without dates can't tell you whether you'll finish on time.

Your Jira hierarchy is already a WBS

Jira's parent-child structure maps onto the levels of a classic WBS. What Jira doesn't have is a time view of that tree with dependencies on it. Here is how each level shows up in Simple Gantt:

WBS level In Jira In Simple Gantt
Project / deliverable A Jira project (or a set of issues found by JQL) One Simple Gantt project
Work package Epic A parent bar whose dates roll up from its children
Activity Story or task A bar, dated from the Jira fields you choose
Smallest piece Subtask A bar nested under its parent
Stage of the project No built-in equivalent Phases, with a color band and dates from their tasks
Key dates and deliverables No built-in equivalent Milestones (diamond markers)

How to turn a WBS into a Gantt chart in Jira

  1. 1. Break the work down in Jira first

    Use epics for work packages, stories and tasks for the activities under them, and subtasks for the smallest pieces. Each item should be something that can be finished and checked, and the children of an item should cover all of its work, no more and no less.

  2. 2. Date the lowest level, not the parents

    Give the stories, tasks and subtasks a start and an end date. In Simple Gantt you choose which Jira fields hold those dates for each project. Leave the epics alone: their dates are calculated from their children, so they stay right when a child moves.

  3. 3. Link the order with Jira issue links

    Record "this has to finish before that starts" as a Jira link. A new Simple Gantt project maps Jira's Blocks link to Finish-to-Start by default, and you can map other link types to Start-to-Start, Finish-to-Finish or Start-to-Finish in the project settings. See the four dependency types if you're not sure which you need.

  4. 4. Open the hierarchy as a Gantt chart

    In Simple Gantt, create a project by picking your Jira project (a JQL query is available as an advanced option). Your epics, stories, tasks and subtasks appear nested on the timeline, with the dependency arrows and the critical path. Not ready to use real data? Start with the demo project.

  5. 5. Add what a WBS leaves out

    Group the work into phases for the stages of the project, mark key dates as milestones, and take a baseline once the plan is agreed, so you can see later how far the schedule moved.

Common mistakes when building a WBS Gantt chart

  • •Typing dates on the parents. A hand-typed epic date drifts from the work beneath it. Date the children and let the parent follow.
  • •Breaking the work down too far. If an item takes an hour, it's a checklist entry, not a WBS level. Stop when a piece is small enough to assign and estimate.
  • •Skipping the links. Without dependencies a Gantt chart is a set of independent bars, and there is no critical path to tell you which delay moves the end date.
  • •Keeping the WBS somewhere else. A spreadsheet WBS next to Jira goes stale. If the breakdown is the Jira hierarchy, the Gantt chart and the work stay the same thing.

Other ways to get a WBS Gantt chart in Jira

Simple Gantt isn't the only route. Jira's own Timeline shows epics and their child issues over time; where it stops is covered in Jira Timeline vs a Gantt chart.

Teams coming from Microsoft Project often look at WBS Gantt-Chart for Jira. Its Marketplace listing describes import and export of MS Project tasks, dependencies and task structures, along with critical path, baselines, milestones and resource monitoring. If MS Project files are part of your process, check that listing for what you need.

Your plan stays on Atlassian infrastructure

Simple Gantt is built on Atlassian Forge and carries the Runs on Atlassian badge: your Jira data is processed and stored within Atlassian's cloud, with no external servers. Details are on our security page.

See your Jira hierarchy as a Gantt chart

Install from the Atlassian Marketplace, pick a Jira project, and your epics, stories and subtasks are on the timeline.

Get Started with Simple Gantt