Jira Timeline Dependencies: How They Work, Why They Hide
You linked two work items in Jira, opened the Timeline, and there is no arrow between them. Or the arrow is there, but it does not tell you what you actually wanted to know: which tasks drive the end date.
This guide covers both situations. First, how dependencies work in Jira’s built-in Timeline and how to create them. Then the usual reasons a dependency does not appear, as a checklist you can work through. Then what the Timeline is not designed to do, so you know when you have reached its limits rather than hit a bug.
A note on vocabulary: Atlassian’s documentation now calls projects spaces and issues work items. This post uses the newer terms where it quotes Jira’s interface, and the older ones elsewhere. They mean the same thing.
How dependencies work in Jira’s Timeline
A dependency on the Timeline is an ordinary Jira issue link. Specifically, it is a link of the Blocks type: one work item blocks the other, or is blocked by it. Atlassian describes a timeline dependency as meaning that one item must be finished before the next one can start.
Before you can use them, three things need to be true:
- A Jira admin has enabled work item linking for the site.
- You have the Link work items permission in the space.
- You are in a software space. Atlassian’s dependency articles are written for software space timelines.
Creating a dependency
There are two ways to add one:
- On the timeline. Hover over a schedule bar so the dots appear on each end, then drag a dot onto the other work item. Jira works out the direction (blocks or is blocked by) from the order the two items are scheduled in.
- From the side panel. Select a work item to open its panel, open the link menu, choose Link work item, pick blocks or is blocked by, and choose the other item.
Because a timeline dependency is just a Blocks link, a link created anywhere else in Jira (from the issue view, for example) shows up too, provided both items are on the same timeline.
Reading and removing dependencies
Select the line between two items to see the details of the dependency, or to remove it. If the dates of the two items overlap, so that the blocked item is scheduled to start before its blocker finishes, the line turns red to flag the risk.
Why a dependency is not showing: a checklist
If the link exists but no line appears, work through these causes in order. The first three account for most cases.
1. Dependencies are switched off in the view
Dependency lines can be hidden. Open View settings at the top right of the timeline and, under Visual details, make sure Dependencies is turned on.
2. The link is not a Blocks link
This is the most common cause. Atlassian’s documentation states that the timeline only shows links of the Blocks type. A relates to link, a clones link, or a custom type your admin created (such as depends on) is saved on the work item but never drawn on the timeline.
Fix: open one of the work items and check the link type in the linked work items section. If it is not blocks or is blocked by, remove it and add a Blocks link instead.
3. The two items are in different spaces
The Timeline is built for a single space, and Atlassian’s documentation says linked work items must come from a single space to show as a dependency. A Blocks link from WEB-12 to API-40 is valid in Jira, but neither space’s timeline will draw it.
Fix: there is no setting for this in the Timeline. Atlassian points cross-space planning to Plans, which is included with Jira Premium and Enterprise. If you are not on those plans, see how to build a roadmap in Jira without Premium.
4. One of the items is not on the timeline at all
A dependency line needs both ends to be visible. If one item is missing from the timeline, its links go with it. Atlassian’s troubleshooting articles list several reasons an item can be missing:
- The board filter excludes it. The timeline uses the board’s JQL. A Kanban filter such as
workType != Epic, for example, removes parent items from the timeline. Atlassian’s suggested fix is to move that clause into the Kanban sub-filter, which affects the board but not the timeline. - It was completed a long time ago. The timeline automatically leaves out items that moved to the Done status category more than a year ago.
- A parent item has no dates. In team-managed spaces, parent items need both a Start date and a Due date. If they were cleared, reschedule the item from the backlog.
- The date fields are missing. If the space’s field scheme does not include Start date and Due date, the timeline asks you to update the space settings. If the Due date field is hidden on work items, recently completed items may not appear.
- It is collapsed or filtered out. A filter at the top of the timeline, or a collapsed hierarchy level, can hide the item. Atlassian’s July 2026 update to software timelines made standalone items and subtasks visible, with settings to hide them again, so what you see depends on how your timeline is configured.
5. The board pulls from more than one space
If the board’s JQL includes work from several spaces, the timeline shows the message “Timelines are designed for a single space” instead of your work. Narrow the filter to one space. This is the same single-space rule as cause 3, applied to the whole board.
6. You cannot create the link in the first place
If the link menu or the drag handles are missing, either work item linking is disabled for the site or you lack the Link work items permission. Both need a Jira admin.
What the Timeline is not designed to do
Once your Blocks links are drawing correctly, you may find the Timeline still does not answer the scheduling questions you have. That is by design: Atlassian positions the Timeline for planning one team’s work in one space. These are the main gaps, as of October 2026.
One dependency type, with no lag
Every timeline dependency means “finish before the next starts”, which is finish-to-start. There is no way to say two tasks must start together (start-to-start), finish together (finish-to-finish), or that one cannot finish until another starts (start-to-finish), and no way to add a lag of a few days. Even in Plans, Atlassian’s documentation says configured link types are all treated as if they were Blocks links. A suggestion to support other dependency types has been open since 2016. For what each of the four types means and when you would use it, see the 4 Jira dependency types explained.
A warning, not a reschedule
The documented behavior when a dependency is violated is a warning: the line turns red. The Timeline does not compute how far the delay pushes the downstream work, or the end date. Moving the dependent items is up to you.
No critical path or slack
The Timeline does not identify the chain of dependent tasks that determines your finish date, or show how much slack every other task has. Atlassian’s critical path suggestion has been open since 2021. If you want to work out the critical path by hand or with a tool, the critical path guide for Jira walks through it.
No baselines
There is no way to save a snapshot of the plan and compare today’s dates against it. A suggestion to add baselines to Plans is still open, and Atlassian’s Timeline documentation does not describe a baseline feature.
One space at a time
As covered in the checklist, dependencies and the timeline itself are limited to a single space. Cross-space work needs Plans on Jira Premium or Enterprise.
None of this means the Timeline is the wrong tool. For one team, one space, and a sequence of work where “this before that” is enough, it is free, already set up, and the dependencies it does draw are useful. For a fuller picture of where it fits, see Jira Timeline vs Gantt chart, and for dependency tracking beyond the Timeline, how to track dependencies in Jira.
How Simple Gantt handles Jira dependencies
Simple Gantt is a Gantt chart app for Jira Cloud, and it is one option if you need what the previous section lists. Here is how it treats dependencies, including the parts that work differently from what you might expect.
It reads the Blocks links you already have. Simple Gantt maps Jira’s Blocks link type to a finish-to-start dependency by default, so the links you created for the Timeline appear as dependency lines without re-entering anything. The mapping lives in the project settings, where each Jira link type is assigned a dependency type.
It models all four dependency types. Finish-to-start, start-to-start, finish-to-finish and start-to-finish are stored, drawn, and used by the critical path calculation. You choose the type when you add a dependency while creating a new task.
Adding a dependency between two existing issues goes through Jira. Today, Simple Gantt cannot create a dependency between two tasks that already exist. For existing issues, add a Blocks link in Jira, and Simple Gantt shows it as a finish-to-start dependency.
It calculates the critical path. Simple Gantt finds the critical path from your dependencies and shows the slack on every other task.
It keeps baselines. Save up to 10 baselines per project and see a variance report of how dates have moved since each one.
It runs on Atlassian Forge, so your Jira data does not leave Atlassian’s infrastructure.
See your Blocks links as a critical path
Simple Gantt reads the dependencies you already have in Jira, calculates the critical path with slack, and lets you save baselines. Your data stays on Atlassian.
Add Simple Gantt to JiraIf your real problem is that the work spans several spaces and you are not on Premium, read how to build a roadmap in Jira without Premium next. It compares the options, including Plans, and is honest about which one fits which situation.
Frequently Asked Questions
- Why is my dependency not showing in the Jira Timeline?
- The most common causes are: the Dependencies option is switched off under View settings, the two work items are linked with a type other than Blocks, the items belong to different spaces (projects), or one of the items is not on the timeline at all because the board filter excludes it, it lacks dates, or it was completed more than a year ago.
- Which link types does the Jira Timeline show as dependencies?
- Only the Blocks link type (blocks / is blocked by). Links such as relates to, clones or a custom depends-on type are stored on the work item but are not drawn on the timeline. A Jira admin must also have work item linking enabled for the site.
- Can the Jira Timeline show dependencies between projects?
- No. Atlassian's documentation says timeline dependencies must link work items from a single space. Cross-space planning is handled by Plans, which is included with Jira Premium and Enterprise.
- Does the Jira Timeline support start-to-start or finish-to-finish dependencies?
- No. A timeline dependency means one item must finish before the next can start, which is finish-to-start. Atlassian's feature request for other dependency types is still open. If you need start-to-start, finish-to-finish or start-to-finish, you need a scheduling tool that stores a type per dependency.