How to Build a Roadmap in Jira Without Premium

· Simple Gantt Team

You want one picture of the work: what happens when, what waits on what, and the dates that matter. In Jira, the feature built for that picture across teams is Plans (formerly Advanced Roadmaps), and it is part of Jira Premium and Enterprise. If your site is on Free or Standard, you do not have it.

That still leaves you several ways to get a working roadmap. This guide covers what your current plan already includes, what Plans would add if you upgraded, and the realistic options for building a roadmap with dependencies and milestones without changing your Jira subscription.

Throughout, “space” is Atlassian’s current name for a Jira project, and “work item” is its name for an issue.

What Jira Free and Standard give you: the space timeline

Every software space on Jira Free (up to 10 users) and Standard has a timeline. In Atlassian’s plan comparison it appears as basic roadmaps. It is a reasonable roadmap for a single team:

  • Epics and their child items over time. Parent items are scheduled from dates you set or from their children’s dates. Child items take their dates from their Start date and Due date, or from their sprint in Scrum spaces.
  • Dependencies. Link two work items with the Blocks link type and the timeline draws a line between them. If their dates overlap, the line turns red.
  • Sprints and releases. Sprints (in Scrum spaces) and releases appear along the top, and you can switch between weeks, months and quarters.
  • Recent improvements. Atlassian’s July 2026 update to software timelines on all Cloud plans added inline editing of status and assignee, bulk actions, color coding by status or epic, standalone items and subtasks on the timeline, and the removal of the previous 5,000 work item limit. Timelines can also be embedded, live and editable, in Confluence.

What it does not do is the part most people mean when they say “roadmap” at the program level:

  • One space only. Atlassian’s documentation is explicit that a timeline can only show work items from one space, and that dependencies must link items within that space.
  • Two levels of hierarchy. The timeline is organized around epics and their children. Levels above epics, such as initiatives, are a Plans feature.
  • One dependency type. Every dependency means “finish before the next starts”. There is no start-to-start or finish-to-finish, and no lag. The guide to Jira Timeline dependencies covers this, and why a dependency may not show, in detail.
  • No dedicated milestones. The closest built-in equivalent is a release, which shows as a marker on the timeline.

If your roadmap fits inside one space and one team, start here. It costs nothing and it is already set up.

What Plans adds, and what it costs

Plans is Atlassian’s advanced planning feature. According to Atlassian’s documentation, it is available only as part of Jira Cloud Premium and Enterprise. It adds:

  • Cross-space planning. A plan combines work items from boards, spaces and filters, including team-managed spaces, into one view across teams or the whole organization.
  • More hierarchy. You can add levels above epics, such as initiatives.
  • Dependencies across the plan. You can see dependencies that affect your timeline, including ones that reach outside the plan, and review them in a dedicated dependencies view.
  • Capacity and scenarios. Plans schedule work against team capacity and velocity, and you can compare alternative scenarios.
  • Auto-scheduling. The auto-scheduler proposes dates from your estimates, dates, dependencies and team assignments, and you review the changes before accepting them.
  • A sandbox. Changes stay in the plan until you choose to apply them to the work items.

Cost. Plans is not sold separately; it comes with the Premium or Enterprise plan for your Jira site. Per-user prices change and depend on your team size, so check Atlassian’s Jira pricing page for current figures rather than relying on a number in a blog post.

What Plans does not add. It is worth knowing before you upgrade for scheduling reasons. Atlassian’s documentation says configured link types in a plan are treated as if they were Blocks links, so a plan still has one dependency type. Atlassian’s public suggestions for critical path analysis and for baselines in Plans are both still open.

If you need cross-team capacity planning, scenarios and initiative-level hierarchy, Plans is the tool built for that job, and upgrading is a sound choice. If what you need is a project schedule with dependencies, milestones, a critical path and a saved baseline, upgrading may not get you there.

Your options for a roadmap without upgrading

Option 1: Stretch the space timeline

Many teams get further with the built-in timeline than they expect by being deliberate about structure:

  1. Keep the roadmap in one space. If an initiative spans spaces only because of how teams were set up, consider tracking the roadmap epics in one space and linking out to delivery work elsewhere.
  2. Use epics as phases. Each epic becomes a phase of work with a date range, and its children roll up underneath.
  3. Use releases as milestones. Turn on Releases in the timeline’s View settings. Atlassian’s own versions tutorial describes versions as milestones to aim for.
  4. Use Blocks links for every real dependency. Only the Blocks type is drawn, so agree as a team to use it for anything that affects sequencing.
  5. Share it where people already look. An embedded timeline in Confluence keeps stakeholders on live data.

Good fit: one team, one space, sequential work. Falls short when: work spans spaces, or you need to know which tasks drive the end date.

Option 2: A spreadsheet or slide roadmap

Export issues to a spreadsheet and draw the bars, or keep a roadmap slide. It is flexible and everyone can read it.

Good fit: an occasional executive summary. Falls short when: dates change, because the copy goes stale the moment someone moves an issue in Jira, and dependencies live only in the drawing.

Option 3: A Gantt app from the Atlassian Marketplace

Marketplace apps add a Gantt chart on top of your Jira issues, without changing your Jira plan. They differ a lot in price, in how they handle dependencies, and in where they process your data. For a side-by-side, see the main Jira Gantt apps compared, and the Jira Timeline vs Gantt chart post for what a Gantt chart adds in general.

Good fit: project scheduling with dependencies, milestones and critical path. Falls short when: you need organization-wide capacity planning and scenarios, which is what Plans is for.

Option 4: Upgrade to Premium

If the features in the Plans list above are the ones you are missing, upgrading is the direct route, and you also get the other Premium features that come with it.

Simple Gantt as one of those options

Simple Gantt is a Marketplace app, and it is our product, so weigh this section accordingly. In Simple Gantt, a roadmap means the issues, phases and milestones of a project laid out over time. Here is what it covers, and what it does not.

What it does:

  • Reads your Jira data. Dates, assignees and sprints come from your Jira issues, and you can show any Jira field as a column.
  • Phases and milestones. Group work into phases and mark key dates as milestones.
  • Dependencies. Finish-to-start, start-to-start, finish-to-finish and start-to-finish are modeled, drawn, and used by the critical path calculation. Your existing Jira Blocks links appear as finish-to-start dependencies by default.
  • Critical path with slack, so you can see which tasks drive the end date.
  • Baselines. Up to 10 per project, with a variance report.
  • Workload by person, without needing estimates.
  • Sprint overlay, project health, and export to CSV, PDF or PNG plus a share link for stakeholders.
  • Runs on Atlassian Forge, so your data does not leave Atlassian’s infrastructure.

What to know before you install:

  • Dependencies between existing issues are added in Jira. You choose a dependency type when you create a new task in Simple Gantt, but you cannot currently add a dependency between two tasks that already exist. For those, add a Blocks link in Jira and Simple Gantt shows it as finish-to-start.
  • It plans projects, not portfolios. There is no capacity planning, scenario modelling or auto-scheduling. If those are the reason you looked at Plans, Plans is the better fit.

A project roadmap on your current Jira plan

Phases, milestones, dependencies, critical path and baselines over your real Jira issues. No Premium upgrade, and your data stays on Atlassian.

Add Simple Gantt to Jira

Which option fits

  • One team, one space, simple sequencing: the space timeline you already have.
  • A summary slide for leadership once a quarter: a spreadsheet or slide, refreshed from Jira.
  • A project with dependencies, milestones and a deadline you have to defend: a Gantt app such as Simple Gantt. The guides to dependency types and critical path in Jira explain what to look for.
  • Many teams, shared capacity, initiative-level planning: Plans on Jira Premium or Enterprise.

Many teams end up combining two of these: the timeline for day-to-day sprint work, and a separate schedule for the dates and dependencies stakeholders ask about.

Frequently Asked Questions

Is Jira Plans (Advanced Roadmaps) available on Jira Standard?
No. Atlassian's documentation describes plans as advanced planning features available only as part of Jira Cloud Premium and Enterprise. Free and Standard include the space timeline, which Atlassian's plan comparison calls basic roadmaps.
Does Jira Standard have a roadmap?
Yes. Every software space on Jira Standard, and on Jira Free, has a timeline, which Atlassian's plan comparison lists as basic roadmaps. It shows epics and their child work over time for one space. Cross-space roadmaps, levels above epics and capacity planning are part of Plans, which comes with Jira Premium and Enterprise.
Can I make a roadmap in Jira for free?
Yes, within limits. Every software space on Jira Free (up to 10 users) and Standard has a timeline that shows epics and their child work over time, with Blocks dependencies, sprints and releases. It covers one space at a time and has no critical path or baselines.
How do I show dependencies on a Jira roadmap without Premium?
Link work items with the Blocks link type. The space timeline draws Blocks links between items in the same space as dependency lines, and turns a line red when the dates overlap. For dependencies across spaces, or dependency types other than finish-to-start, you need Plans or a Marketplace app.
How do I add milestones to a Jira roadmap?
Jira has no dedicated milestone item on the timeline. The common approach is to use releases (fix versions), which appear as markers on the space timeline when enabled in View settings. Atlassian's own tutorial describes versions as milestones to aim for. Some Marketplace apps add true milestone markers.