Switching from BigGantt to Simple Gantt
Most of what is on a Jira Gantt chart was never stored in the Gantt app. Your issues, their dates, assignees, hierarchy and issue links live in Jira, and they come with you. What lives only inside a Gantt app, such as its own baselines, groupings or tasks that aren't Jira issues, does not: Simple Gantt has no importer for other Gantt apps. This page sets out what moves, what you set up again, and the order to do it in.
Still deciding?
If you haven't settled on switching yet, start with the five things to check when choosing a Jira Gantt app. This page assumes you've decided and want to know what the move involves.
What comes across, and what you set up again
| Part of your plan | Where it lives | In Simple Gantt |
|---|---|---|
| Issues, summaries, assignees, status | Jira | Read directly. Nothing to import |
| Start and end dates | Jira fields | Read from the date fields you choose for the project. Drag a bar and the new dates are written to the Jira issue, where Jira lets that field be edited |
| Hierarchy | Jira | Epics, stories and tasks, and subtasks nested; parent dates roll up from children |
| Dependencies made as Jira issue links | Jira | Blocks shows as Finish-to-Start by default; map other link types to any of the four types in project settings |
| Sprints | Jira | Shown with the sprint overlay |
| Baselines | The Gantt app | Take a new baseline (up to 10 per project). Earlier baselines don't carry over |
| Groupings and key dates | The Gantt app | Recreate as phases and milestones |
| Tasks that aren't Jira issues | The Gantt app | Recreate as Simple Gantt custom tasks, or as Jira issues |
| Saved views and filters | The Gantt app | Each Simple Gantt project is a Jira project or a JQL query |
Not sure what your current setup stores itself? The rule of thumb: if you can see it on the Jira issue, it's in Jira.
A switching checklist
-
1. List what lives only in the old app
Baselines you still compare against, groupings, markers, and any tasks that were never Jira issues. Export or note what you want to keep before you change anything.
-
2. Install Simple Gantt alongside it
Installing Simple Gantt changes nothing in Jira, so both can read the same issues while you compare.
-
3. Create a project from your Jira project
Pick the Jira project, or use a JQL query if the plan spans projects or needs a filter. To look around without touching real data, start with the demo project.
-
4. Check the dates and the dependency arrows
Confirm the start and end date fields are the ones your team uses, and that the link types you rely on are mapped. Blocks is mapped to Finish-to-Start by default; see the four dependency types for the others.
-
5. Rebuild the plan layer
Add phases and milestones, recreate any non-Jira tasks, and take a baseline of the plan as it stands today, so variance is measured from the switch.
-
6. Move the team, then retire the old app
Once people are planning in Simple Gantt, decide what to do with the old app's own data before you uninstall it.
Know this before you switch
- •Auto-scheduling, what-if scenarios and resource management. BigGantt's listing describes all three. Simple Gantt doesn't offer auto-scheduling or what-if scenarios today, and its workload view shows load by assignee from dates rather than managing resources. If your team relies on these, keep that in mind.
- •Linking two existing issues. In Simple Gantt you can add a dependency while creating a task. To link two issues that already exist, link them in Jira and the arrow appears on the chart.
- •Change history is opt-in. Simple Gantt can record changes made in the app, but recording is off by default; turn it on per project if you want it.
Runs on Atlassian
Simple Gantt is built on Atlassian Forge and carries the Runs on Atlassian badge: your Jira data is processed and stored within Atlassian's cloud, with no external servers. Details are on our security page.
Related reading
- Choosing a BigGantt alternative Five things to check before you switch Gantt apps.
- The 4 Jira dependency types explained Finish-to-Start, Start-to-Start, Finish-to-Finish and Start-to-Finish, with when to use each.
- Dependencies and critical path All four dependency types, critical path highlighting and slack on every task.
- Baselines and change history Save up to 10 snapshots and compare planned vs actual on the timeline.